Customers planning to install a micro-embedded generation system (PV or battery energy storage system) must ensure they have a generation system compliant meter.
This list will assist customers in determining if their current meter is compliant, or if they need either a new meter or a meter reprogram for their meter to become compliant.
A generation system compliant meter needs to be bi-directional and capture both generated and consumed quantities from the grid.
Reprogrammable meters
The following meters are available to be reprogrammed if the customer is applying for a solar PV or battery energy storage system connection.
A reprogrammable meter fee will apply. See our Alternative Control Service (ACS) pricelist for fees
Reprogrammable meters
- EDMI MK7C
- EDMI MK7C-DR
- EDMI MK10D (three-phase)
- Secure Liberty 120
- Liberty 120S
- S211
Do I need a meter upgrade or change?
The following meters will need to be replaced if the customer is applying for a solar PV or battery energy storage system connection.
A replacement meter fee will apply. See our Alternative Control Service (ACS) pricelist for fees.
- M2 / M2S / M3S
- A1LL
- YL5
- SMD (three-phase)
- WF3
- C1B Itron
- E1000 / E1000S
- CM170BC / CM170
- 3030
- EDMI MK10WC / MK10AWC
- EDMI MK10AEDMI MK10CT
- Secure 500B
- EDMI MK10CT
- EDMI MK10A
- EDMI MK7A (only if changing to a type 2 meter. Please clarify with Power and Water if unsure).