Power and Water is upgrading the Sadadeen Substation to increase reliability and security of the Alice Springs power network.
This $11.85 million project will replace the existing building and install new 11kV Air Insulated Switchgear (AIS). The new switchgear will replace existing systems which is approaching the end of its life.
The upgrade will support up to 30 jobs during the construction and will also support Alice Springs hardware, freight and hotel businesses.
All works are scheduled to be complete by April 2020 and the new equipment is expected to be fully operational by August 2020.
Power and Water aim to have as little impact as possible on adjacent neighbourhoods and residents while works take place.
For more information, read the media release from Minister for Renewables, Energy and Essential Services in the Northern Territory Government Newsroom.
Ends